Gas units in South Tripoli restarted their work.

Thanks to the efforts of the engineers and technicians of the power station south of Tripoli, the second gas unit with a capacity of 100 MW was recently restarted.

As a result of the accumulation of garbage adjacent to the station south of Tripoli and the rise of smoke (aerosol) with heavy fog, which led to the blockage of air filters and the exit of units (second, third, fourth and fifth) from service, and thus the south Tripoli station suspended its operations and lost a value of 400 megawatts.

In addition to the inability of the company on the discharge of the energy produced due to the injury of the major transport circles in southern Tripoli, which led to an increase in the electrical network deficit.